Pipeline
15.0 KM Black Oil Pipe Line
Bauang Private Power Corporation tasked MIESCOR to provide detailed engineering of 15.0 Kilometer Black Oil line from Caltex depot located at Poro Point in San Fernando to Bauang Diesel Power Plant. The project was the alternative scheme of fuel conveyance to the power plant.


Tongonan, Leyte Steam Piping
MIESCOR engineering provided fabrication drawings of PNOC country steam piping as support to our MIESCOR construction team.
Dulangan and Bansud Mini-Hdyro Projects
MIESCOR provided fabrication drawings of penstock from fore bay to powerhouse.