Malolos-Calumpit and Malolos-Tabang 69 kV Lines

Malolos-Calumpit and Malolos-Tabang 69 kV Lines

Project Scope

The uprating works for the Malolos–Calumpit and Malolos–Tabang 69 kV lines involve the replacement of existing ACSR conductors with STACIR conductors to increase the lines’ current-carrying capacity and enhance overall system reliability of MERALCO in the area.
The main scope of work includes conductor replacement, line reconfiguration, and installation of new armor rods. The project was divided into five (5) job orders, implemented progressively from February to June 2025. To facilitate the works, scheduled power interruptions were conducted nightly, during which the DUS-STL team mobilized from Pasig to Bulacan to execute the required construction and line uprating activities.

Project Gallery

CONTACT US

We’d Love To Know More About Your Project

Contact Us Banner

The Meralco Industrial Engineering Services Corporation (“MIESCOR”) complies with Republic Act No. 10173, otherwise known as the “Data Privacy Act of 2012”, in collecting and handling your personal data.

We request for complete and accurate information to fully assist you in exercising your rights as a data subject under the Data Privacy Act of 2012.

We shall only use personal data provided in this form to address your request.