Project: Engineering, Procurement, and Construction of 138 kV Transmission Line Client: Mindanao Energy Systems, Inc. (MINERGY)
Mindanao Energy Systems, Inc. (MINERGY) has contracted Meralco Industrial Engineering Services Corporation (MIESCOR) to undertake the Engineering, Procurement, Construction and Commissioning (EPC) of its wholly-owned affiliate, Minergy Coal Corporation's, Tagoloan-Balingasag 138kV sub-transmission line. The sub-transmission line will interconnect the 110MW coal fired power plant of Minergy Coal in Balingasag, Misamis Oriental to the distribution system of CEPALCO. Rated at 138 kV and configured as a double-circuit in steel pole structures, the 37-km line will be constructed using 785 MCM ACSR conductors with 3/8 inch diameter Optical Fiber Ground Wire (OFGW) as its neutral. Its route will be along the National highway.